Monday 18 April 2011

Let's Get to Know our Neighbours ( Post event)

I was there after 1pm. Buffet style food was served and a slide show on the recent upgrading works are presented. Not many residents were seen around that time. A rough guess, probably around 30 pax. I was told later that time, more residents joined.

I'm glad to meet up with few owners and friends. Fellow JMB were seen updating residents on the recent developement as well as their future plan. It is definitely a great event for owners to mingle around and get the latest news. I guess the next event will be the AGM which scheduled in the next 2 months. Hope more owners can join us!



Monday 4 April 2011

Let's Get to Know Our Neighbours (Updated on 6th April 2011)

Please be informed that JMB is organizing a gathering for all owners with details as following:

Date: Sunday 17th April 2011 (postponed due to request from residents who are away on the 10th April)
Time: 12- 3 pm
Venue: Badminton Hall at Club House


Residents are encouraged to join this event to get to know each other better.

Friday 1 April 2011

Repair and Upgrading Works from July 2010 to March 2011

These are the few updates I wish to updates you guys especially on the upgrading works that were carried out since July 2010 to March 2011.
1) August 2010
CCTV at Main Entrance/Exit
Installation of additional cameras to enhance security level.

2) September 2010
Lifts button
Installation of Perspex cover for lift button panel.

3) October 2010
Main entrance walkway
Installation of flexible barricade pole to separate the resident and visitor's lane

4) October 2010
Car park lot for rent
Additional 77 bays of car park lot open for owner/resident to rent.

5) December 2010
Pedestrian walkway gate
Installation of the steel gate to restrict/screen entry of visitor/residents.

6) February 2011
Games room
Installation of glass partition at club house as an additional games room.

7) February 2011
Low voltage room/Main switch room (electrical)
Calibration of the switch boards at block A, B, C and D.

8) March 2011
Swimming pool
Repair works on the dislocated swimming pool tiles.

9) April 2011
Visitor car park lot
Extra visitors car park lot at level LG and LGA-In progress.

Related Posts with Thumbnails